|Objective=1) Inventory of requirements for a flood proof electricity grid; 2) Flood proof grid spatial planning measures (layer 2), and 3) Duplicable spatial measures model for resilient NSR electricity grids
|Objective=1) Inventory of requirements for a flood proof electricity grid; 2) Flood proof grid spatial planning measures (layer 2), and 3) Duplicable spatial measures model for resilient NSR electricity grids
|Flood risk=Sea flooding
|Flood risk=Sea flooding
|Target=1 - 381.182 inhabitants
2 - 1 electricity grid operator
|Responsible person=CNTR 00110
}}
}}

Versie van 13 jun 2019 09:35

Pilot objective/goal

The aim was to better understand the vulnerability (including cascading effects) of the electricity supply network (medium and low voltage) in Zeeland and recommend robust spatial measures to make it more flood proof (Nelen & Schuurmans, 2018). Thus, the main focus of the pilot is on Layer 2 (spatial planning) benefiting Layer 3 (crisis management) of the MLS approach.



}

























Country: The Netherlands
Coordinate 51° 29' 56.12" N, 3° 36' 39.84" E
Pilot manager authority: Province of Zeeland
Objective:
  • Inventory of requirements for a flood proof electricity grid;
  • Flood proof grid spatial planning measures (layer 2), and
  • Duplicable spatial measures model for resilient NSR electricity grids
Flood risk: Sea flooding